Project Summary Information

Location
Sector Economic Sub-Sector Rural Transport
Technical Assistant Yem Savong Nature of Project Infrastructure
Name ជួសជុលផ្លូវក្រាលក្រួសក្រហមធ្លក
Objective ងាយស្រួលធ្វើដំណើរនិងដឹកជញ្ជូនកសិផលរបស់ប្រជាពលរដ្ឋ
Related contract(s) 250502/16/01-01
Created By Administrator Mobile

Project Detail Information

Annual budget available

Calendar Year National Transfer * Local Revenue Carry Over Other Total
2016 10,618 0 0 0 10,618
  • opened on 30-Jun-2016 with 3 contractor(s) contract awarded 250502/16/01-01

* Budget planned : partial amount from intergovermental transfer
* LOC. Revenue : Local revenue if available.

Mark source of fund to be use

There is no funding source associated with this project; which mean the project will build up on Commune/Sangkat fund.

Beneficiary:

No Village Beneficiary Households
Total Women
1 Samraeuy 576 295 135
2 Trapeang Santey 441 226 111
3 Thlok 848 427 201
Total 1,865 948 447

Project outputs and estimation cost (Form 14/15).

Nr. Village Description Qty Unit Cost Total Operations
1 Thlok Earth road Repair [ 1010101 ]
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 1,420.940 Volume of earth (m3)
0.640 km 3,353 2,146
2 Thlok Earth road Repair [ 1010101 ]
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 1,024.000 Volume of earth (m3)
1.500 km 5,648 8,472
Estimated cost 10,618

Remark:

  • All output will be locked after technical clearance is completed.

Evironmental safeguard clearance (Form 3)

Impact

This project did not require environment study.

Reason

 

Land safeguard clearance (Form 3)

Impact

This project did not require land acquisition report.

  • Public

 

Highland people safeguard clearance(Form 3)

Impact

This project did not require highland people report.

 

Sign-Off

Feasibility study completed on 28-Apr-2016
Technical clearance sign-off 06-Jun-2016