Project Summary Information

Location [ 31509 ] Kampong Cham \ Stueng Trang \ Preaek Bak
Sector Economic Sub-Sector Rural Transport
Technical Assistant OUK KEOmony Nature of Project Infrastructure
Name ជួសជុលផ្លូវក្រូសក្រហមព្រែកបាក់-ទំនប់ខ្នាច
Objective ងាយស្រួលធ្វើដំណើរ និងដឹកជញ្ជូនកសិផលរបស់ប្រជាពលរដ្ឋ
Related contract(s) 031509/16/01-01
Created By Administrator Mobile

Project Detail Information

Annual budget available

Calendar Year National Transfer * Local Revenue Carry Over Other Total
2016 17,763 0 0 0 17,763
  • opened on 03-Mar-2016 with 6 contractor(s) contract awarded 031509/16/01-01

* Budget planned : partial amount from intergovermental transfer
* LOC. Revenue : Local revenue if available.

Mark source of fund to be use

  • Commune/Sangkat Fund

Beneficiary:

No Village Beneficiary Households
Total Women
1 Preaek Bak 2,709 1,421 758
Total 2,709 1,421 758

Project outputs and estimation cost (Form 14/15).

Nr. Village Description Qty Unit Cost Total Operations
1 Preaek Bak Laterite road Repair [ 1010102 ]
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 7,315.000 Volume of earth (m3)
2.000 km 8,561 17,122
2 Preaek Bak Single pipe culvert 0.6m diameter New [ 1010301 ]
  • Dimension #1 : 600.000 Diameter (mm)
  • Dimension #2 : 6.000 Length(m)
1.000 Place 641 641
Estimated cost 17,763

Remark:

  • All output will be locked after technical clearance is completed.

Evironmental safeguard clearance (Form 3)

Impact

This project did not require environment study.

Reason

 

Land safeguard clearance (Form 3)

Impact

This project required land acquisition report.

  • Voluntary
Approval date18-Jan-2016

 

Highland people safeguard clearance(Form 3)

Impact

This project did not require highland people report.

 

Sign-Off

Feasibility study completed on 21-Jan-2016
Technical clearance sign-off 21-Jan-2016