Contract Summary Information

Area Name
Contract 250503/16/01-01 Technical SupervisorYem Savong
Project's Name ជួសជុលផ្លីវដីសល្ងៀង
SectorEconomic Sub-SectorRural Transport
Contractor Horng Sophorn, [ Horng Sophorn ]
Competitive biddingYes ( 27-Jun-2016 ) Number of contractor3
Contract sign date (Form 50) 10-Jul-2016 Guarantee period6 Month
Planned work start date10-Jul-2016 Planned work completion date30-Jul-2016
Created By Administrator Mobile
RILGP Status Ineligible Confirmation

Contract Detail Information

Cost by fund source:

Fund Source Cost
Commune/Sangkat Fund 14,144
Total 14,144

Number of contractor: 2/3

Director's Name Contractor Bid Value Discount Rate Rejected Reason
1 Horng Sophorn Horng Sophorn 13,672 USD -3 % No
2 Sao Kaknika Sao Kaknika 13,720 USD -3 % No
 



Contract Value:

Nr. Village Description Bid In Contract Actual quantity Unit Cost
/ Estimated
Discount Rate Total
1 Lngieng [ 1010302 ] Single pipe culvert 0.8m diameter New
  • Dimension #1 : 800.000 Diameter (mm)
  • Dimension #2 : 5.000 Length(m)
3.000 Place 3.000 Place 3.000 Place 1,000
est. 1,266
-21 %
3,000
2 Lngieng [ 1010101 ] Earth road Repair
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 2,504.160 Volume of earth (m3)
0.600 km 0.600 km 0.600 km 10,400
est. 11,407
-9 %
6,240
3 Lngieng [ 1010302 ] Single pipe culvert 0.8m diameter New
  • Dimension #1 : 600.000 Diameter (mm)
  • Dimension #2 : 5.000 Length(m)
3.000 Place 3.000 Place 3.000 Place 1,200
est. 1,016
18 %
3,600
4 Lngieng [ 1010103 ] Natural Gravel road Repair
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 81.920 Volume of earth (m3)
0.040 km 0.040 km 0.040 km 10,400
est. 6,450
61 %
416
5 Lngieng [ 1010101 ] Earth road Repair
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 5,791.000 Volume of earth (m3)
0.040 km 0.040 km 0.040 km 10,400
est. 4,869
114 %
416
Contract cost without tax 13,672
Total tax amount (3% or 10%) (0 %) 0
Total contract cost include tax 13,672



Actual work start date 20-Jul-2016 Actual work completion date 29-Aug-2016
PIM 3.13.1 start of work meeting date PIM 3.13.7 section A/B 80% payment approval date.

 

Service delivery/Construction Progress:

Date Progress Report By Note
10-Aug-2016 50 % Administrator
29-Aug-2016 100 % Administrator

* Remark: List above will show how far the work (construction) had been progressed; please update the progress as soon as it become available. For infrastructure monthly progress can be update from TSO report except the report of 50% and 100% complete which required approval from CC.

Please register contract payment base on "Contract Register" sheet submit from Provincial Treasury.

Date Source Description Gross Net Tax Verified
No payment register recorded.
Actual Payment Cumulative To Date (A) 0 USD 0 USD 0 USD
Contract Value (B) 14,144 USD  
Balance 14,144 USD  (Depletion Rate=(A/B)*100) 100 %

Tax Deduction Rate: 0 %

No incident reported so far.