Contract Summary Information

Area Name [ 30711 ] Kampong Cham \ Kang Meas \ Sour Kong
Contract 030711/16/01-01 Technical SupervisorLeng heng
Project's Name ផ្លូវក្រាលក្រួសធម្មជាតិ
SectorEconomic Sub-SectorRural Transport
Contractor Chhim Vutha, [ Chhim Vutha ]
Competitive biddingYes ( 21-Apr-2016 ) Number of contractor7
Contract sign date (Form 50) 29-Apr-2016 Guarantee period6 Month
Planned work start date01-May-2016 Planned work completion date23-Jul-2016
Created By Administrator Mobile
RILGP Status Ineligible Confirmation

Contract Detail Information

Cost by fund source:

Fund Source Cost
Commune/Sangkat Fund 17,925
Total 17,925

Number of contractor: 5/7

Director's Name Contractor Bid Value Discount Rate Rejected Reason
1 Poch Thong Poch Thong 19,095 USD -55 % No
2 Sen Kokser Sen Kokser 23,450 USD -45 % No
3 Chhim Vutha Chhim Vutha 17,925 USD -58 % No
4 Chhin Darin Chhin Darin 19,830 USD -54 % No
5 Ket Menglaiy Ket Menglaiy 20,100 USD -53 % No
 



Contract Value:

Nr. Village Description Bid In Contract Actual quantity Unit Cost
/ Estimated
Discount Rate Total
1 Anlong Ak Kaeut [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 4.000 Width (m)
  • Dimension #2 : 7,773.000 Volume of earth (m3)
1.500 km 1.500 km 1.500 km 5,650
est. 12,688
-55 %
8,475
2 Anlong Ak Kaeut [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 3.800 Width (m)
  • Dimension #2 : 3,298.000 Volume of earth (m3)
0.500 km 0.500 km 0.500 km 5,400
est. 14,667
-63 %
2,700
3 Boeng Sang Kaeut [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 3.000 Width (m)
  • Dimension #2 : 7,859.000 Volume of earth (m3)
1.350 km 1.350 km 1.350 km 5,000
est. 12,121
-59 %
6,750
Contract cost without tax 17,925
Total tax amount (3% or 10%) (0 %) 0
Total contract cost include tax 17,925



Actual work start date 14-May-2016 Actual work completion date 15-Jul-2016
PIM 3.13.1 start of work meeting date PIM 3.13.7 section A/B 80% payment approval date.

 

Service delivery/Construction Progress:

Date Progress Report By Note
23-Jun-2016 50 % Administrator
15-Jul-2016 100 % Administrator

* Remark: List above will show how far the work (construction) had been progressed; please update the progress as soon as it become available. For infrastructure monthly progress can be update from TSO report except the report of 50% and 100% complete which required approval from CC.

Please register contract payment base on "Contract Register" sheet submit from Provincial Treasury.

Date Source Description Gross Net Tax Verified
No payment register recorded.
Actual Payment Cumulative To Date (A) 0 USD 0 USD 0 USD
Contract Value (B) 17,925 USD  
Balance 17,925 USD  (Depletion Rate=(A/B)*100) 100 %

Tax Deduction Rate: 0 %

No incident reported so far.