Contract Summary Information

Area Name [ 30708 ] Kampong Cham \ Kang Meas \ Roka Ar
Contract 030708/16/01-01 Technical SupervisorLeng heng
Project's Name ផ្លូវក្រាលក្រួសធម្មជាតិ
SectorEconomic Sub-SectorRural Transport
Contractor Chhin Phearun, [ Chhin Phearun ]
Competitive biddingYes ( 11-Apr-2016 ) Number of contractor8
Contract sign date (Form 50) 22-Apr-2016 Guarantee period6 Month
Planned work start date25-Apr-2016 Planned work completion date15-Jun-2016
Created By Administrator Mobile
RILGP Status Ineligible Confirmation

Contract Detail Information

Cost by fund source:

Fund Source Cost
Commune/Sangkat Fund 17,110
Total 17,110

Number of contractor: 7/8

Director's Name Contractor Bid Value Discount Rate Rejected Reason
1 Kry ya Kry ya 23,200 USD -31 % No
2 Ouk Sopheak Ouk Sopheak 18,850 USD -44 % No
3 Chhim Vutha Chhim Vutha 17,400 USD -48 % No
4 Chhin Darin Chhin Darin 18,270 USD -46 % No
5 Chhin Phearun Chhin Phearun 17,110 USD -49 % No
6 Monh Soun Seriroth 26,100 USD -23 % No
7 Ket Menglaiy Ket Menglaiy 17,980 USD -47 % No
 



Contract Value:

Nr. Village Description Bid In Contract Actual quantity Unit Cost
/ Estimated
Discount Rate Total
1 Svay Sranaoh Ti Muoy [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 3.500 Width (m)
  • Dimension #2 : 8,474.000 Volume of earth (m3)
1.500 km 1.500 km 1.500 km 5,900
est. 12,085
-51 %
8,850
2 Chrouy Krabau Ti Pir [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 3.500 Width (m)
  • Dimension #2 : 1,898.000 Volume of earth (m3)
0.600 km 0.600 km 0.600 km 5,900
est. 9,942
-41 %
3,540
3 Chrouy Krabau Ti Muoy [ 1010103 ] Natural Gravel road Upgrade
  • Dimension #1 : 3.500 Width (m)
  • Dimension #2 : 4,132.000 Volume of earth (m3)
0.800 km 0.800 km 0.800 km 5,900
est. 11,985
-51 %
4,720
Contract cost without tax 17,110
Total tax amount (3% or 10%) (0 %) 0
Total contract cost include tax 17,110



Actual work start date 04-May-2016 Actual work completion date 23-Jun-2016
PIM 3.13.1 start of work meeting date PIM 3.13.7 section A/B 80% payment approval date.

 

Service delivery/Construction Progress:

Date Progress Report By Note
07-Jun-2016 50 % Administrator
23-Jun-2016 100 % Administrator

* Remark: List above will show how far the work (construction) had been progressed; please update the progress as soon as it become available. For infrastructure monthly progress can be update from TSO report except the report of 50% and 100% complete which required approval from CC.

Please register contract payment base on "Contract Register" sheet submit from Provincial Treasury.

Date Source Description Gross Net Tax Verified
No payment register recorded.
Actual Payment Cumulative To Date (A) 0 USD 0 USD 0 USD
Contract Value (B) 17,110 USD  
Balance 17,110 USD  (Depletion Rate=(A/B)*100) 100 %

Tax Deduction Rate: 0 %

No incident reported so far.